Product change notifications (PCN) is the way of informing customers of upcoming changes related to Teltonika products. This includes outward appearance adjustments, hardware improvements, firmware changes, changes to package contents, etc.
This page stores information regarding changes to the FMB920. Below you will find a list of both upcoming and already implemented changes sorted from newest to oldest (top to bottom).
2019.03.01: new eco friendly box
Effective March 2019, FMB920 trackers will be shipped with a new eco friendly box.
Change description
|
---|
Change type
|
Packaging
|
Detailed description
|
Improved and more environmentally friendly packaging box
|
Old version:
|
New version:
|
Change reasons
|
The new box is better for the environment
|
Product release date
|
March 2019
|
Affected products
|
---|
Model
|
Affected order codes
|
Order code changes
|
FMB920
|
FMB920*******
|
No changes
|
Change impact
|
---|
Risk assessment
|
No risk factors encountered with this change
|
Suggested implementation plan
|
No implementation plan needed
|
Acknowledgement of PCN receipt
|
---|
If no feedback is received within two weeks after the issue date of this notification - Teltonika may accept that this change has been tacitly accepted and can implement the change as indicated above
|
2019.02.20: Top Tampography Changes
We would like to inform you, that tampography of FMB920 device was updated in factory on the 20th of February.
Change description
|
---|
Change type
|
External/visual
|
Detailed description
|
Top tampography design changed
|
Old Version:
|
New Version:
|
Change reasons
|
1. Updated Teltonika address to Saltoniskiu st. 9B-1 2. Added WEEE label. (WEEE - Waste from Electrical and Electronic Equipment)
|
Product release date
|
Updated tampographs will be used from the time when the stock will be sold all leftovers. Planned date: week 10
|
Affected products
|
---|
Model
|
Affected order codes
|
Order code changes
|
FMB920
|
FMB920*******
|
No changes
|
Change impact
|
---|
Risk assessment
|
No risk factors encountered with this change
|
Suggested implementation plan
|
No implementation plan needed
|
Acknowledgement of PCN receipt
|
---|
If no feedback is received within two weeks after the issue date of this notification - Teltonika may accept that this change has been tacitly accepted and can implement the change as indicated above
|